Heera Redevelopment project included the installation of 4 new Well-Head Platforms, 8 new Rigid Pipelines, 3 Flexi lines, 3 cables and modification to 7 existing platforms.

Client: ONGC India (Operator) and Punj Lloyd India (EPCC Contractor).

January 1, 2008

  • heera2
  • heera3

The project was executed via Sempec/ZEE office in Jakarta and the fabrication of the Platforms were carried in Kencana Yard in Lumut, Malaysia.

ZEE’s Scope of Work:

  • Design of the 4 new platforms
  • Modification of 7 existing platforms
  • Design of 8 rigid pipelines
  • Design of 3 flexi lines
  • Design of 3 cables
  • Construction supervision at Malaysian Yard
  • Transport and Installation Engineering