Project Description

Lima Filed Assets are approximately 30 years old. Due to the heavy extraction of Oil/Gas the complete field has subsided approximately 12 meters.

Client: OPERATOR – Pertamina & EPPC CONTRACTOR – TIMAS

March 21, 2016

Lima Filed Assets are approximately 30 years old. Due to the heavy extraction of Oil/Gas the complete field has subsided approximately 12 meters. PERTAMINA wishes to prolog the production life of the field and decide to carry out the lifting of the 4 platforms in the field simultaneously. This is the first time such a project has been undertaken.

Scope included the relocation of existing equipment, modify all piping and E&I works, Structural re-analysis and structural modification. The complete project was undertaken by Synergy / ZEE (JV Partners)

 

ZEE’s Scope of Work

  • Structural modifications and re-analysis
  • Structural Integrity of the Hydraulic Jacking System
  • Local F.E. Analysis