It was required to relocate the Crude Oil Offloading Facilities to deeper water to facilitate Offloading from larger tankers.

Client: Petrochina Company Ltd Indonesia (Operator).

January 1, 2008

 

  • tuban2
  • tuban3

The new terminal was relocated approximately 1.5km from the existing position. The project involved the installation of a new PLEM, submarine pipeline from existing PLEM to new PLEM, Installation (Mooring) of SPM and FSO.

ZEE’s Scope of Work:
ZEE was asked to carry out FEED Study Detail Engineering and prepare the technical documents for RFQ.

The study involved the design of:

  • Submarine Pipeline
  • New PLEM
  • Mooring Analysis

– Check the integrity of System and the design of Anchor Piles

  • Cost Estimation
  • Compiling Technical documents for RFQ