Diesel Storage Terminals
- Client :- PT.PETRO STORINDO ENERGY
-
Project Type :-
Offshore
-
Location :-
Indonesia
Overview
PT. Petro Storindo Energi (PSE) intends to implement a new 75,000 m3 diesel storage terminal & related facilities at Sangatta, Kutai Timur, East Kalimantan. McConnel Dowell have been nominated by PSE to perform onshore and offshore works. PT. Dwisatu Mustika Bumi as MC Dowel subcontractor are responsibility to install the subsea pipeline sistem including loading/unloading facilities at fixed mooring dolphin.
| Engineering Services |
|---|
General
- Basis of Design (BoD)
- Project Execution Plan (PEP)
- Plot Plan & Terminal Layout
Process
- PFDs & P&IDs
- Equipment Datasheets (pumps, filters)
- Cause & Effect & HAZOP Reports
Mechanical
- Storage Tank Design & GA Drawings
- Pump Sizing & Specs
- Equipment Layouts
Piping
- Piping Layouts & Isometrics
- Line List & Valve List
- Pipe Stress Analysis
Civil/Structural
- Tank Foundations & Bund Walls
- Pipe Rack & Equipment Supports
- Drainage & Containment Plans
Electrical
- Single Line Diagrams (SLD)
- Power & Lighting Layouts
- Earthing & Lightning Protection
Instrumentation & Control
- Instrument Index & Datasheets
- Loop Diagrams & I/O List
- SCADA/PLC Control Logic
Safety & Fire Protection
- Firewater Network Layout
- Firefighting Equipment Plan
- ESD & Safety System Design
Environmental/Utilities
- Stormwater & Spill Containment
- Venting & Vapor Control Design
- Utility Line Diagrams
Construction & Commissioning
- Material Requisitions (MR)
- Test Procedures & Commissioning Plans
- As-Built Drawings & O&M Manuals